Brown field factory


Branche

Consumer & Food

Company size

> 18,600 employees

Project duration

5 years and 3 months

Dimension

22,000 m² net floor area; EUR 60 million

North Rhine-Westphalia

Customer

Our customer is one of the largest system providers for the food processing industry. It is one of the market and technology leaders in its business segments.

Services

 Construction of the production, assembly and testing areas:

  • Factory planning and project management for the construction of the separation production plant during all planning phases
  • Develop plant structure and directions of expansion
  • Concept of parts production as forklift free factory 
  • Planning of assembly lines and cells with integrated test field
  • Dimensioning of the production logistics areas
  • Support procurement process for new production equipment as central chip conditioning and disposal, flexible production system
  • Integration of the construction planning with the general contractor tendering process
  • Support of the building owner during construction process